Nanollose Completes Stage 1 Pilot Equipment Orders as Perth Premises Talks Progress

Nanollose Pilot Facility Stage 1 equipment is now fully ordered and paid for, but a Perth lease still stands between Nanollose and Stage 2 commissioning targeted for Q3 CY2027.
By Josua Ferreira -
  • All Stage 1 Pilot Facility equipment is ordered and paid for, with the final key pieces due over the next 2 months and several items already delivered.
  • The lease is the bottleneck: Nanollose has no executed lease on a Western Australian site, and the Stage 1 equipment can't be fully installed without one.
  • Stage 2 long lead items are expected to be ordered in November, alongside a finalised Stage 2 roadmap.
  • Stage 2 commissioning is targeted for Q3 CY2027, conditional on securing a suitable facility and permits.
  • Stage 1 will generate the operating data to finalise Stage 2 equipment, so the next round of spending rests on scaled-up results rather than laboratory assumptions.
Summarise with AI:

Stage 1 Pilot Facility equipment ordered and paid for

Nanollose Limited (ASX: NC6) has completed procurement for the first stage of its Pilot Facility program, with all Stage 1 equipment ordered and paid for and delivery of the final key pieces expected over the next 2 months. Several items have already been delivered.

The update marks a move from planning into execution on the Company-controlled Pilot Facility in Western Australia, its principal operating objective for FY2027 (refer ASX announcements of 8 April 2026 and 31 August 2026). With the equipment committed, procurement is no longer an open question on the pilot pathway.

What Stage 1 delivers for process development

Equipment and modular approach

Stage 1 equipment consists of commercially available items, consistent with the modular approach previously set out to shareholders. It includes:

  • A 200-litre disintegrator
  • Hammermill
  • Filter press
  • Reactors
  • Dewatering equipment

Data before Stage 2 spending

Stage 1 is designed to provide an expanded in-house operating environment where Nanollose can increase the scale and efficiency of its process development work. It will also generate the data required to finalise equipment selection and configuration for Stage 2.

That allows investment in Stage 2 equipment to be based on scaled up operating data generated through Stage 1, rather than laboratory assumptions.

Why pilot scale matters

A pilot facility is an intermediate step between laboratory testing and full commercial production. Running a process at larger volumes shows whether it holds up outside the lab.

For Nanollose, this applies to the ‘Tree-Free’ cellulose it produces by fermentation and uses as an input for its Nullarbor™ fibres, MicroGel™ horticultural medium and emerging animal-free and plastic-free leather-like materials.

Stage Purpose Status Timing
Stage 1 Expand in-house process development capability and generate operating data Equipment ordered and paid for Remaining deliveries expected over the next 2 months
Stage 2 Key pilot-production phase Long lead items expected to be ordered in November Commissioning targeted Q3 CY2027, subject to a suitable facility and permits

Stage 2 and the partner opportunity

Stage 2 is the key pilot-production phase, targeting production capacity sufficient to support multiple meaningful partner collaborations. Planning work has identified several long-lead items required for this phase.

Securing and fitting out suitable premises is now the immediate operational priority, as a fit-for-purpose Western Australian site is required before the Stage 1 equipment can be fully installed and commissioned. Nanollose has assessed numerous sites across the Perth metropolitan area, and negotiations are progressing on preferred premises.

Andrew Moullin, CEO and Managing Director

“Every piece of Stage 1 equipment is now ordered and paid for, and that is a tangible step from planning into execution… Stage 2 is the important phase. That is where we will move from process development into producing the volumes required for meaningful partner evaluation and customer collaboration…”

What happens next for Nanollose’s pilot program

The announcement sets out the following milestones:

  1. Final Stage 1 equipment deliveries: expected over the next 2 months.
  2. Lease on preferred premises: negotiations are progressing, and the Company will update shareholders once a lease is executed.
  3. Stage 2 long lead items: the Company expects to order these in November, with ordering anticipated before the end of November.
  4. Stage 2 program roadmap: expected to be finalised next month (November), providing greater clarity around the development timeline and key implementation requirements.
  5. Stage 2 commissioning: targeted for Q3 CY2027, subject to securing a suitable facility and required permits.

Nanollose Pilot Program Upcoming Milestones

For investors, the update reports Stage 1 procurement complete and the focus shifting to premises, with the Stage 2 roadmap and long lead orders the next items on the Company’s schedule.

Don’t Miss the Next Biotech Breakout

Get FREE ASX news delivered to your inbox within minutes of release, with in-depth analysis already done. Join 20,000+ subscribers who see market-moving announcements the moment they break. Click the “Free Alerts” button at Big News Blast to stay ahead of the market.


Frequently Asked Questions

What is a pilot facility in biomaterials?

A pilot facility is an intermediate step between laboratory testing and full commercial production. Running a process at larger volumes shows whether it holds up outside the lab.

What equipment is included in the Nanollose Pilot Facility Stage 1?

Stage 1 includes a 200-litre disintegrator, hammermill, filter press, reactors and dewatering equipment, all commercially available items. Everything has been ordered and paid for, with final key deliveries expected over the next 2 months.

When will Nanollose's Stage 2 pilot facility be commissioned?

Stage 2 commissioning is targeted for Q3 CY2027, subject to securing a suitable facility and required permits. Long lead items are expected to be ordered in November.

What does Nanollose need to do next on its pilot program?

Nanollose needs to execute a lease on preferred Western Australian premises, as the Stage 1 equipment can't be fully installed without a site. It also expects to finalise its Stage 2 roadmap and order long lead items in November.

What is Nanollose's Tree-Free cellulose used for?

Nanollose produces Tree-Free cellulose by fermentation and uses it as an input for Nullarbor™ fibres, MicroGel™ horticultural medium and emerging animal-free, plastic-free leather-like materials.

Josua Ferreira
By Josua Ferreira
Partnership Director
Josua Ferreira holds a Bachelor of Commerce in Marketing and Advertising and brings a background in publication, business development, and ASX market storytelling. He has worked with listed companies across the resource sector and broader market, combining sharp commercial instincts with a genuine commitment to keeping investors informed.
Learn More
Companies Mentioned in Article

Breaking ASX Alerts Direct to Your Inbox

Join +20,000 subscribers receiving alerts.

Join thousands of investors who rely on StockWire X for timely, accurate market intelligence.

About the Publisher