X2M Connect Signs Agreement for 10MW Queensland AI Data Centre Site

X2M Connect has locked in binding 60-day exclusivity over a 10MW Queensland AI data centre site with a $250m estimated project cost, lifting its capacity under agreement to 20MW and above $500m in aggregate project value.
By Josua Ferreira -
  • X2M has secured 60 days of binding exclusivity over a 10MW Queensland data centre site with development approval and an estimated project cost of $250m.
  • Commercial terms are still to be agreed, with binding long-form agreements targeted within 90 days, so this is not yet a completed contract.
  • The site has a 2.5MW grid connection today, while the final 7.5MW depends on behind-the-meter renewable generation expected by the end of calendar 2028.
  • X2M now has 20MW under agreement and more than $500m in aggregate estimated project cost, against a non-binding pipeline above 200MW.
  • The $250m is project cost, not revenue, and X2M expects to earn a margin, recurring AI management revenue and a potential token revenue share with no figures disclosed.
Summarise with AI:

X2M signs agreement for 10MW AI-enabled data centre in Queensland

X2M Connect Limited (ASX: X2M) has signed an agreement with a Queensland developer (the “Developer”) for a 10MW AI-enabled data centre site with development approval. X2M intends to deliver and manage the facility under its Managed Delivery service.

X2M has been granted binding exclusivity over the data centre site and its power capacity for 60 days. Commercial terms are still to be agreed, with binding long-form agreements targeted within 90 days, so the arrangement is a signed agreement rather than a completed long-form contract.

Key facts from the announcement:

  • 10MW AI-enabled data centre site with development approval
  • $250m estimated project cost
  • 60-day binding exclusivity over the site and its power capacity
  • 90-day target for binding long-form agreements

The approvals and power already in place are expected to deliver faster commercialisation.

Grid connection and approvals already in place

Staged power build to the full 10MW

The site has an existing 2.5MW grid connection, together with local government development approval for a data centre. The facility will be delivered in stages, with the initial stage using the existing grid capacity.

The Developer intends to build behind-the-meter renewable generation to supply the final 7.5MW under a power purchase agreement, taking the facility to the full 10MW. This power is expected to be available to the site by the end of the 2028 calendar year, and the announcement also refers to power being generated on the site for 10 years.

Mohan Jesudason, Chief Executive Officer

“…this site already has energy and local government approval in place, with planned behind-the-meter generation to carry it to the full 10MW…”

X2M expects the existing approvals and power to result in earlier project completion and revenue recognition.

How X2M expects to earn from the project

The 10MW data centre is planned to be delivered through X2M’s compute and GPU partnerships. It is currently expected that X2M will manage the elements of the full project cost and earn a margin on the project.

X2M is also expected to earn recurring revenue from AI-enabled management of the facility, along with a potential token revenue share. The announcement does not disclose revenue figures.

The $250m is the estimated project cost, not X2M revenue.

Managed Delivery covers the design, engineering, supply, installation and commissioning of the facility. This is followed by ongoing AI-enabled platform services and management for the life of the asset.

Why AI-enabled data centres need less power

Data centres depend on electricity, and available grid capacity limits the pace of data centre build-out. Energy is described in the announcement as the binding constraint on data centre growth.

X2M’s AI-enabled platform is expected to produce the same compute from fewer electricity megawatts. It is intended to manage energy, cooling and environmental systems across both grid-supplied and behind-the-meter supply.

Behind-the-meter generation refers to on-site power generation. X2M looks for developers and customers able to build their own behind-the-meter micro grid, which gives the facility energy security independent of the grid.

According to the announcement, more compute from every approved megawatt is a key reason customers partner with X2M.

Regional strategy and 20MW now under agreement

A de-risked regional approach

X2M is targeting data centre facilities in low-density population regions of Queensland and the Northern Territory, rather than large metropolitan campuses. This places less demand on the grid and requires a smaller capital commitment.

As part of its due diligence process, power, land and government approval are assessed at every site before a binding agreement is signed.

Pipeline progress

Together with its first binding agreement (ASX: 27 August 2026), X2M now has 20MW of data centre capacity under agreement. The aggregate estimated project cost is more than $500m.

X2M Capacity Pipeline Metrics

The first binding agreement carried an estimated project cost above $250 million and was conditional solely on development approval, with X2M expecting to recognise the full project cost as revenue and earn a margin.

The prospective pipeline remains above 200MW, with the majority of sites in Queensland. This pipeline comprises a series of non-binding agreements, so it should not be read as contracted capacity.

Agreement Capacity Date or status Estimated project cost Notes
First binding agreement 10MW ASX: 27 August 2026 Not separately disclosed Design work confirmed initial capacity of 10MW
This agreement 10MW 23 October 2026 $250m Binding exclusivity for 60 days, with long-form agreements targeted within 90 days
Total under agreement 20MW n/a More than $500m (aggregate) Alongside a pipeline above 200MW

Next steps centre on converting the balance of the pipeline, including the partnership agreements already announced, and on delivery. Mohan Jesudason said: “Our focus is now on delivery and on converting the balance of our pipeline, including the partnership agreements already announced.”

Investors exploring how the pipeline might convert into binding agreements can read our detailed coverage of the Gateway DC partnership, which outlines the 120MW initial campus, the 2GW+ roadmap and the due diligence under way on X2M’s prospective sites.

Don’t Miss the Next Tech Breakout on the ASX

Join 20,000+ investors getting FREE breaking ASX news delivered within minutes of release, complete with in-depth analysis. Click the “Free Alerts” button at Big News Blast to receive tech, AI and data centre updates the moment market-moving announcements break.


Frequently Asked Questions

What is behind-the-meter generation at a data centre?

Behind-the-meter generation is on-site power generation that supplies a facility directly rather than through the grid. X2M looks for developers able to build their own behind-the-meter micro grid, which gives the facility energy security independent of the grid.

What did X2M Connect announce for its 10MW data centre in Queensland?

X2M signed an agreement with a Queensland developer for a 10MW AI-enabled data centre site with development approval and an estimated project cost of $250m. It holds binding exclusivity for 60 days, with long-form agreements targeted within 90 days.

Is the $250m data centre project cost X2M's revenue?

No, the $250m is the estimated project cost, not X2M revenue, and the announcement does not disclose revenue figures. X2M expects to manage elements of the project cost and earn a margin, plus recurring management revenue and a potential token revenue share.

How much data centre capacity does X2M have under agreement?

X2M has 20MW of data centre capacity under agreement across two 10MW sites, with an aggregate estimated project cost above $500m. Its prospective pipeline exceeds 200MW but is made up of non-binding agreements.

When will the full 10MW of power be available at the X2M site?

The site has an existing 2.5MW grid connection for the first stage. The remaining 7.5MW of behind-the-meter renewable generation is expected to be available by the end of the 2028 calendar year.

Josua Ferreira
By Josua Ferreira
Partnership Director
Josua Ferreira holds a Bachelor of Commerce in Marketing and Advertising and brings a background in publication, business development, and ASX market storytelling. He has worked with listed companies across the resource sector and broader market, combining sharp commercial instincts with a genuine commitment to keeping investors informed.
Learn More
Companies Mentioned in Article

Breaking ASX Alerts Direct to Your Inbox

Join +20,000 subscribers receiving alerts.

Join thousands of investors who rely on StockWire X for timely, accurate market intelligence.

About the Publisher