NEXTDC Slashes FY27 Revenue Outlook by $140M as Melbourne Power Delay Bites

NEXTDC's M3 Melbourne power delay has knocked about A$140 million off FY27 revenue and EBITDA guidance and cut capex by A$750 million, but A$8.7 billion of liquidity keeps the balance sheet firm.
By Josua Ferreira -
  • NEXTDC has cut FY27 Underlying EBITDA guidance to A$245m to A$265m from A$385m to A$410m, with about A$140 million removed because of the affected M3 Melbourne contracts.
  • Jemena does not expect to restart its suspended 66kV works before February 2027, pushing the next M3 grid supply increase and dependent billing into FY28.
  • FY27 capex guidance falls to A$4,500m to A$5,000m, a like-for-like cut of 17% to 19% once A$230 million of capitalised interest is stripped out.
  • Liquidity of A$8,675 million and a first debt maturity in December 2029 give NEXTDC runway, though full access to the A$6,700 million of undrawn debt depends on billing profiles and covenant headroom.
  • The capex review outcome lands at the 20 November AGM, with the Victorian election on 28 November and the M3 Stages 6 and 7 planning decision not expected until 2027.
Summarise with AI:

NEXTDC revises FY27 guidance as M3 Melbourne power delay defers contracted revenue

NEXTDC (ASX: NXT) revised its FY27 net revenue, Underlying EBITDA and capital expenditure guidance on 21 October 2026, after Jemena Electricity Networks (Vic) Ltd works delays deferred the next increase in grid supply to its M3 Melbourne data centre. The revision excludes the affected M3 contracts from net revenue and Underlying EBITDA guidance.

The company reported liquidity of A$8,675 million at 30 September 2026 and said it remains in compliance with its financial covenants. It has also said it will refocus capital expenditure on near term contracted customer capacity.

The affected capacity “remains under contract, subject to the customer’s rights”, according to the company. The announcement frames the issue as one of timing, with delivery and billing deferred, and does not describe a confirmed loss of the contracts.

Craig Scroggie, Chief Executive Officer and Managing Director

“With M3 revenue deferred, we have paused projects not backed by customer contracts and put that capital behind the capacity our customers have already contracted…”

Revised FY27 guidance at a glance

The revised net revenue and Underlying EBITDA ranges are materially lower than the guidance issued on 27 August 2026. Capital expenditure guidance has also been reduced.

FY27 Guidance Revision Breakdown

The August guidance was set alongside NEXTDC’s FY26 full-year results, which beat the top end of guidance and projected more than 50% growth on FY26 actuals.

Metric Previous guidance (27 Aug 2026) Revised guidance Change
Net revenue A$615m to A$640m A$475m to A$500m Excludes affected M3 contracts
Underlying EBITDA A$385m to A$410m A$245m to A$265m Excludes affected M3 contracts
Capital expenditure A$5,250m to A$5,750m A$4,500m to A$5,000m Reduction of A$750m, or 13% to 14%

What drives the revision

The revised net revenue and Underlying EBITDA guidance excludes the revenue and attributable EBITDA of the affected customer contracts at M3 Melbourne, including capacity already billing and any potential service level credits. The August guidance included approximately A$140 million of each of net revenue and Underlying EBITDA from those contracts, and their exclusion is the main reason for the reductions.

Capacity already billing is excluded because, while parts of Jemena’s works are suspended, existing grid supply at M3 cannot be relied on to support the full contracted power ramp in data halls already delivered.

NEXTDC’s actual FY27 results will include the contribution of the affected contracts. Service level credits payable on those contracts could reduce Underlying EBITDA below the revised guidance, which is given on a constant currency basis and before any fair value movement on investment property.

Investors exploring how contracted demand converts into billing can read our detailed coverage of the 565MW forward order book, which tracks the 740MW contracted utilisation position and the FY30 conversion timeline.

Understanding the M3 Melbourne power delay

A data centre earns revenue from capacity it can power. Where a grid distributor controls the supply of electricity to the site, network works by that distributor can determine when contracted capacity is delivered and billed.

For investors, this means revenue is linked to power availability, not only to completed buildings. The timing of third-party infrastructure is therefore a key variable. Jemena is the electricity distributor that supplies power to M3.

Timeline and key dependencies

  1. Jemena suspended parts of its 66kV line augmentation works in September 2026, citing safety concerns and lack of access to work sites arising from community and stakeholder opposition, and the local council, as the relevant road authority, not giving its consent while further community consultation takes place.
  2. Jemena has formally notified NEXTDC that it does not expect to recommence the works before February 2027.
  3. Based on Jemena’s current indicative estimate, NEXTDC expects the next increase in grid supply during FY28, with delivery and billing of the dependent contracted capacity to follow shortly thereafter.
  4. Later increases depend on upstream transmission projects to install new transformers at the Brooklyn Terminal Station. NEXTDC now expects the first of these to be completed later than previously expected, though they do not separately affect the revised FY27 guidance.
  5. The Victorian Government’s planning decision on M3 Stages 6 and 7 (application PA2604231, lodged February 2026) is not now expected until 2027. Caretaker conventions are due to begin on 3 November 2026, ahead of the State election on 28 November 2026.

Customer contracts and management response

NEXTDC said it has a good relationship with the affected customer and will continue to engage constructively with it. Construction of the M3 data halls is continuing within the existing buildings.

The company is working with the customer on a revised power ramp and with Jemena to bring forward the delivery of power to M3.

The affected contracts provide for service level credits where capacity is delivered late or is not fully powered and, in some circumstances, give the customer rights to terminate. NEXTDC is assessing the potential implications under those contracts, including whether relief is available to it under the force majeure and other relevant provisions.

NEXTDC also intends to continue and build on its community engagement around M3 through a community engagement plan for the construction and operation of M3, overseen by the Board.

Capital discipline and balance sheet strength

Capex refocused on contracted capacity

Revised FY27 capex of A$4,500m to A$5,000m includes approximately A$500m of reimbursable customer fitout and approximately A$230m of capitalised interest. The previous guidance did not include capitalised interest.

Before capitalised interest, the revised guidance is approximately A$4,270m to A$4,770m. That represents a like for like reduction of approximately A$980m, or 17% to 19%, which differs from the headline 13% to 14% reduction.

NEXTDC has put all new development projects and land acquisitions on hold for the foreseeable future and is eliminating all material discretionary capital expenditure. The Board has committed to announcing the outcome of its capex review by the Annual General Meeting on 20 November 2026, and will also evaluate capital recycling opportunities, including the potential sale of selected development sites not required in the near term.

Liquidity and covenants

Liquidity at 30 September 2026 was A$8,675 million. This is non-IFRS financial information and has not been subject to audit or review. Its components were:

  • A$1,275 million of cash
  • A$6,700 million of undrawn senior debt facilities
  • The A$700 million Hybrid Securities B Delayed Draw Series, which is committed, subject to customary conditions, and may be drawn until 15 April 2027

NEXTDC remains in compliance with its maintenance financial covenants as at 30 June 2026, the most recent half-yearly test date, and expects to comply at the next test date of 31 December 2026. These covenants are a gearing ratio of not more than 60% and an interest cover ratio of at least 1.5 times.

The earliest scheduled debt maturity is December 2029, being the A$1,500 million Facility A revolving loan facility maturing on 3 December 2029. Holders of the Convertible Notes may require NEXTDC to redeem them on 17 September 2029.

One caveat applies. NEXTDC’s ability to draw all of its A$6,700 million undrawn senior debt facilities while continuing to comply with those covenants will depend on the timing of drawdowns and on expected billing profiles, and delays to grid supply at M3 Melbourne could be a material change to those profiles.

The Subordinated Notes, Hybrid Securities and the A$1,100 million of 1.75% Subordinated Convertible Notes due 2031, issued on 17 September 2026, carry no maintenance financial covenants.

What investors should watch next

The announcement points to several upcoming events:

  1. Investor briefing at 9:30am (AEDT) on 21 October 2026.
  2. Annual General Meeting and capex review outcome on 20 November 2026.
  3. The Victorian State election on 28 November 2026, and the later M3 Stages 6 and 7 planning decision, not expected until 2027.
  4. Half-year results to 31 December 2026, which will reflect the fair value effect on investment properties, not yet quantified.
  5. An update on the FY27 contribution of the affected contracts, which NEXTDC said it will provide when it can reliably estimate it.

Get Tech News Before the Market Moves

Join 20,000+ investors receiving FREE breaking ASX tech news within minutes of release, with in-depth analysis and the full announcement included. Click the “Free Alerts” button at Big News Blast to get market-moving updates the moment they break and stay ahead of the market.


Frequently Asked Questions

What is the NEXTDC M3 Melbourne power delay?

Jemena suspended parts of its 66kV line augmentation works in September 2026, deferring the next increase in grid supply to NEXTDC's M3 Melbourne data centre. NEXTDC now expects that increase in FY28, with delivery and billing of the dependent contracted capacity to follow shortly after.

How much has NEXTDC cut its FY27 guidance?

Net revenue guidance falls to A$475m to A$500m from A$615m to A$640m, and Underlying EBITDA to A$245m to A$265m from A$385m to A$410m. The August guidance included about A$140 million of each from the affected M3 contracts.

Has NEXTDC lost the affected M3 Melbourne contracts?

No loss has been confirmed, and the company says the capacity remains under contract, subject to the customer's rights. The contracts do allow service level credits for late delivery and, in some circumstances, customer termination.

How much liquidity does NEXTDC have after the guidance revision?

NEXTDC reported liquidity of A$8,675 million at 30 September 2026, made up of A$1,275 million of cash, A$6,700 million of undrawn senior debt and a A$700 million hybrid delayed draw. The earliest scheduled debt maturity is December 2029.

When will NEXTDC announce its capex review outcome?

The Board has committed to announcing the outcome of its capex review by the Annual General Meeting on 20 November 2026. It will also evaluate capital recycling, including possible sales of development sites not needed in the near term.

Josua Ferreira
By Josua Ferreira
Partnership Director
Josua Ferreira holds a Bachelor of Commerce in Marketing and Advertising and brings a background in publication, business development, and ASX market storytelling. He has worked with listed companies across the resource sector and broader market, combining sharp commercial instincts with a genuine commitment to keeping investors informed.
Learn More
Companies Mentioned in Article

Breaking ASX Alerts Direct to Your Inbox

Join +20,000 subscribers receiving alerts.

Join thousands of investors who rely on StockWire X for timely, accurate market intelligence.

About the Publisher